ELNT — With a Little Help from Our Friends
Thanks to the dedication of ESCO and the cooperation of all our project partners, the Evergreen Lake North Trail project is moving along on schedule and on budget.
- the support wall is complete;
- the water transmission line has been placed;
- Upper Trail concrete work began in early August; and
- Lower Trail contours and build-out are underway.
The current detour for westbound vehicle traffic along the construction zone will be in place 24/7 until the completion of major construction. Barring unexpected events, the contractor is hopeful to remove the current one-way traffic detour through the construction zone by early September. (After the detour is removed, alternating one-way traffic may be required intermittently to complete final construction activities.)
In the meantime, please stay safe and use designated detours — and remember no pedestrians are permitted in the construction zone or the roadway next to the construction.
Thank you Evergreen for hanging in there to help achieve this major improvement for our community.